[llvm-dev] [cfe-dev] [7.0.0 Release] Schedule proposal
Hans Wennborg via llvm-dev
llvm-dev at lists.llvm.org
Tue Jun 12 01:37:31 PDT 2018
On Thu, Jun 7, 2018 at 6:56 PM, <paul.robinson at sony.com> wrote:
>> Proposal:
>>
>> - 1 August 2018: Branch; RC1 soon after
>> - 22 August 2018: RC2; all lose ends should be tied up by now
>> - 5 September; final tag, release a few days later (don't slip past
>> first half of September)
>>
>> What do you think?
>>
>> I'm particularly keen to hear from those helping to test the release,
>> and from downstream consumers of the branch.
>
> As a downstream consumer, Sony is okay with the proposed schedule.
> --paulr
Thanks! I've added the schedule to the website.
- Hans